4160_Site visit, Pile Driving Day 1
Onsite today to drive piling on Bents 1 & 2, Contractor has layed out both Bents
Crane is setup and ready to start driving.Pile are driving odd, three out of four on Bent 1 hit refusal around 12'-14' but pile 1 has drove to 27' and still going. contractor has had to order pile to finish it.Bent 2 pile are driving deeper than plan but pile 5 only drove to 13', the rest have drove to 22', 28', and 44'
Crane is setup and ready to start driving.Pile are driving odd, three out of four on Bent 1 hit refusal around 12'-14' but pile 1 has drove to 27' and still going. contractor has had to order pile to finish it.Bent 2 pile are driving deeper than plan but pile 5 only drove to 13', the rest have drove to 22', 28', and 44'